Construction Procedures

Upon receiving the investor’s request

the consolidated construction procedures are conducted in the following phases:

  1. Issuing the location conditions for the cadastre parcel suitable for construction – from the day of obtaining all special conditions, permits and other documents --> no later than 5 working days
  2. Issuing the construction permit – from the day of the submission of the request --> no later than 5 working days

Upon receiving the application:

Based on registering the construction work, issuing the verification for receiving the application without delay, provided that the complete documentation has been submitted.

  • Registering the construction works to receive acceptance/rejection --> 5 working days
  • Subsequently, submitting the request for infrastructure installations --> 3 working days

Issuing the occupancy permit, upon receiving the submission of the request --> no later than 5 working days

Issuing the final approval upon receiving the submission of the request --> no later than 5 working days

In total: 28 working days